[solution] » Complete the following problems: The following project is at the

Brief item decscription

Step-by-step solution file


Item details:

Complete the following problems: The following project is at the
More:

Complete the following problems:

  • The following project is at the end of its first week. Find the cost and schedule variances, the cost performance index, the schedule performance index and the estimate at completion.

Task

Predecessors

Duration in days

Planned Value ($)

Actual Cost ($)

Percent Complete

A

None

2

500

650

100

B

None

3

1000

1500

100

C

A

2

200

300

50

D

A

5

600

600

20

E

B ,C

6

1200

550

10

To do this exercise, it is best to start with a Gantt chart depicting the task relationships.

CV  A= -150, B= -500, C= -100, D= 0, E= 650     CPI ________________

SV ______________________      SPI ________________

EAC _____________________



  • Using the following information, calculate the cost performance index and the schedule performance index. Then calculate the estimate at c

Planned value: 6700

Earned value: 6100

Actual costs: 7300

Budget at completion: 38900

CPI _______________________                    SPI  _____________________________

EAC ______________________



  • The following project is at the end of its third week. Find the cost and schedule variances, the cost performance index, the schedule performance index and the estimate at completion.

Task

Predecessors

Duration in days

Planned Value ($)

Actual Cost ($)

Percent Complete

A

None

3

600

650

100

B

A

5

1000

1500

100

C

A

2

200

300

100

D

A

5

1000

600

100

E

B ,C

6

1200

1200

100

F

C

10

10000

12000

75

G

F

7

700

0

0

H

G

8

1600

0

0

To do this exercise, it is best to start with a Gantt chart depicting the task relationships.

CV ______________________     CPI ________________

SV ______________________      SPI ________________

EAC _____________________


  • Mary is the project manager for a web design project for Newberry Pet Foods. So far in the six weeks (of the twelve week project), Mary's team has completed five tasks which had a combined planned value of $7800. However, the team spent $8200 to complete those tasks. She has five additional tasks to complete the project.  What are the PV, EV, AC, CV, SV, CPI, and SPI for Mary's project? 



  • Consider the following information:

Expected weeks

Calculate the following:

CV __________________

SV __________________

CPI __________________

SPI __________________

EAC __________________

Duration at Completion _______________


take place. three warehouses will be bulk The use profit advantages

 

used and wn contributions.

 

Our intention to. equity for current company owners and tax

 


 

Other hand available. But we n half...

 







About this question:
STATUS
Answered
QUALITY
Approved
ANSWER RATING

This question was answered on: Feb 21, 2020

PRICE: $24

Solution~000604515.zip (18.37 KB)

Buy this answer for only: $24

This attachment is locked

We have a ready expert answer for this paper which you can use for in-depth understanding, research editing or paraphrasing. You can buy it or order for a fresh, original and plagiarism-free copy (Deadline assured. Flexible pricing. TurnItIn Report provided)

Pay using PayPal (No PayPal account Required) or your credit card. All your purchases are securely protected by PayPal.
SiteLock

Need a similar solution fast, written anew from scratch? Place your own custom order

We have top-notch tutors who can help you with your essay at a reasonable cost and then you can simply use that essay as a template to build your own arguments. This we believe is a better way of understanding a problem and makes use of the efficiency of time of the student. New solution orders are original solutions and precise to your writing instruction requirements. Place a New Order using the button below.

Order Now